Months |
Tentative construction schedule |
Installments to be Paid |
At the time of Booking |
|
10% of BSP |
With in 60 days of Booking |
|
10% of BSP |
At the time of Allotment |
|
10% of BSP + 50% EDC & IDC |
Bhoomi Pujan\On start of excavation |
|
5% of BSP + 50% EDC & IDC |
With in 2 month of Bhoomi Pujan |
on foundation laying\or start of construction |
5% of BSP +25% of PLC+25%of Parking 25% of Club Membership |
With in 4 month of Bhoomi Pujan |
on completion of foundation |
5% of BSP +25% of PLC+25%of Parking 25% of Club Membership |
With in 6 month of Bhoomi Pujan |
on completion of 2nd floor slab |
5% of BSP +25% of PLC+25%of Parking 25% of Club Membership |
With in 8 month of Bhoomi Pujan |
on completion of 4th floor slab |
5% of BSP +25% of PLC+25%of Parking 25% of Club Membership |
With in 10 month of Bhoomi Pujan |
on completion of 6th floor slab |
5% of BSP |
With in 12 month of Bhoomi Pujan |
on completion of 8th floor slab |
5% of BSP |
With in 14 month of Bhoomi Pujan |
on completion of 10th floor slab |
5% of BSP |
With in 16 month of Bhoomi Pujan |
on completion of 11th floor slab |
5% of BSP |
With in18 month of Bhoomi Pujan |
on completion of 12th floor slab |
5% of BSP |
With in 20 month of Bhoomi Pujan |
on completion of Brick work |
5% of BSP |
With in 22 month of Bhoomi Pujan |
on start of internal plaster |
5% of BSP |
With in 24 month of Bhoomi Pujan |
on start of external plaster |
5% of BSP |
on possession |
|
5% of BSP + IBMS +Power backup+ Registration charges+ other charges as applicable |